Addendum 1 for RFQ

Addendum 1 for RFQ
Published On: September 19, 2022Categories: Social Media Blog

ADDENDUM 1

DATE: 9/16/22

PROJECT: RFQ #2022

ARCHITECTURAL/ENGINEERING SERVICES FOR NEW POST OAK SAVANNAH GCD DISTRICT OFFICES, EDUCATION AND MEETING CENTER

OWNER: POST OAK SAVANNAH GROUNDWATER CONSERVATION DISTRICT

TO: Prospective Engineers or Architects

This Addendum forms part of and modifies the original RFQ which may be found at https://posgcd.org/category/social-media-blog/, with additions noted below:

There was no attendance by any prospective engineer or architect at the mandatory site visit.  Therefore, two items are hereby modified:  

  1. Site Visit is hereby no longer mandatory.  If desired, a prospective engineer/architect may go and view and walk the site and may ask questions of General Manager Gary Westbrook which will then be sent out to all prospective engineers/architects as an addendum.
  2. The deadline has been extended in an effort to ensure that there is sufficient notice of and interest in the RFQ.  NEW DEADLINE IS October 14, 2022.

END OF ADDENDUM 1